Huawei FusionDC1000A Commissioning Manual page 44

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario)
Figure 4-5 Emergency light
Step 2 Remove the protective cover of the emergency light.
Step 3 Remove the red pin of the emergency light. The emergency light turns on.
Figure 4-6 Removing the red pin
Step 4 Reinstall the protective cover of the emergency light.
Step 5 Turn on the upstream switch for the emergency light power cable.
The emergency light turns off, and the power indicator turns on.
Step 6 Press the red button of the emergency light. The emergency light turns on. When
you release the red button, the emergency light turns off.
Issue 01 (2021-04-20)
NO TE
Copyright © Huawei Technologies Co., Ltd.
4 Commissioning Core Devices
38

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r021c00

Table of Contents