Cable Connections To The Power Supply And Distribution System; Grounding The Smart Module - Huawei FusionModule500 V100R021C10 User Manual

Smart mini data center
Hide thumbs Also See for FusionModule500 V100R021C10:
Table of Contents

Advertisement

FusionModule500 Smart Mini Data Center
User Manual
4.
4.3.2 Cable Connections to the Power Supply and Distribution
System

4.3.2.1 Grounding the Smart Module

1.
2.
Issue 01 (2020-11-30)
Figure 4-54 Binding cables in a bending area
Ensure that the cable ties are wrapped and secured in the same direction and
do not generate interference with subsequent operations, as shown in
4-55.
Figure 4-55 Direction for securing cable ties
Connect the ground point in the cabinet to the general ground bar.
Connect the general ground bar in the cabinet to the floor ground bar or
collective ground bar.
Copyright © Huawei Technologies Co., Ltd.
4 Installation Guide
Figure
99

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fusionmodule500-su61a12s

Table of Contents