FusionModule500 Smart Mini Data Center
User Manual
Procedure
Step 1 Determine the cabinet position based on the engineering layout diagram.
Step 2 Place the cabinet at the correct installation position.
Step 3 Level the cabinet using a wrench.
● Use a measuring tape to check that the vertical distance between the top of
● If the leveling height of the cabinet does not meet the requirements, the
Issue 01 (2020-11-30)
NO TICE
the 2000 mm high cabinet and the floor is 2000 mm (+3 mm). Then use a level
to check that the cabinet is level.
cabinet cannot be opened or closed properly.
NO TE
● To ensure the cabinet steadiness, adjust all the six anchor bolts at the bottom of the
cabinet in place.
● After leveling the anchor bolts in the first and last rows, use a flat-head screwdriver to
level the anchor bolts in the middle row until they are in close contact with the ground.
● Do not remove the anchor bolts. Otherwise, rework is required if the cabinet height
does not meet requirements.
● Anchor bolt adjustment method: Wrench an anchor bolt clockwise to elevate a cabinet
leg, or wrench an anchor bolt anticlockwise to lower it. The anchor bolts can be
adjusted within a range of 0-8 mm.
● Levelness check standard: Ensure that the cabinet is level in width and depth directions
when leveling the cabinet. Put a level at the bottom of the cabinet in width and depth
directions and check that the air bubble is in the middle between the two lines marked
on the glass tube.
Copyright © Huawei Technologies Co., Ltd.
4 Installation Guide
69