Installation Manual – BTS3606 Cabinet Installation
Airbridge BTS3606&3606A CDMA Base Station
Figure 2-10 Leveling the lower support
V. Conducting Insulation Test
To conduct an insulation test, proceed as follows:
1)
Set the multimeter to "MΩ".
2)
Connect the two probes to the paint-free place of the base and the expansion
bolt.
3)
If the resistance is larger than 5 MΩ, the insulation is properly done. The
installation ends here. Otherwise, go to step 4.
4)
Check whether any insulating covering or insulating washer is missing or
damaged. If any, replace with new parts and then conduct the insulation test
again. Otherwise, reinstall the expansion bolts and conduct the insulation test.

2.5 Installing Assemblies on Antistatic Floor

This section details the procedures of installing lower supports and A600 supports on
the antistatic floor.