2.5.1 Installation Flowchart

Figure 2-11 shows how to install cabinet assemblies (support and lower support) on
the antistatic floor.
Start
Position the cabinet
Remov e the
floor framew ork
Locate the support
at the side of
anti-static floor
Fix the support
Install the
low er support
Lev el the
low er support
Conduct
insulation test
End
Figure 2-11 Installation flowchart of support and lower support on antistatic floor

2.5.2 Installation Procedure

The following describes the procedure of installing assemblies on the antistatic floor.
OK
Check the
insulating parts
Failed
OK
Huawei Technologies Proprietary
Chapter 2 Installing Cabinet Assemblies
Damaged
or missing
Repair/replace
the parts
Repeat
insulation test
2-12