Mechanical installation
3.3 Assembly
Removing the shipping and handling monitors prior to commissioning
CAUTION
The shipping and handling monitors must be removed before commissioning the converter.
Failure to observe the transport indicators during operation of the converter may cause
damage to the equipment.
3.3.2.4
Unpacking
Unpacking
Check the delivery against the delivery note to ensure that all the items have been delivered.
Check that the cabinet is intact and has not been damaged.
The packaging material must be disposed of in accordance with the applicable country-
specific guidelines and rules.
3.3.2.5
Required tools
To install the connections, you will require:
● Spanner or socket spanner (w/f 10)
● Spanner or socket spanner (w/f 13)
● Spanner or socket spanner (w/f 16/17)
● Spanner or socket spanner (w/f 18/19)
● Hexagon-socket spanner (size 8)
● Torque wrench from 5 Nm to 50 Nm
● Screwdriver, size 2
● Screwdriver Torx T20
● Screwdriver Torx T30
A socket wrench kit with two long extensions is recommended.
48
Converter cabinet units
Operating Instructions, 03/2012, A5E03263466A