Procedure
Step 1 Install the app on the reserved pad (see the commissioning guide) and connect
the pad to the network over the WiFi hotspot of the data center.
Step 2 Specify the user name and password for the app on the reserved pad and log in to
check that the app works properly.
Step 3 Remove the charging cable from the failed pad.
Step 4 Remove the failed pad from the support and install the reserved pad on the
support.
Step 5 Connect the charging cable to the reserved pad.
----End

5.4.18 Replacing the Smart Screen

Impact on the System
The smart screen cannot be used.
Preparations
Procedure
Step 1 Turn off the switch on the side of the smart screen.
Step 2 Remove the power and communications cables from the smart screen.
Step 3 Remove the old smart screen from the door box and install the spare smart screen
on the door box.
Issue 02 (2022-07-30)
Tools: ESD wrist strap, ESD gloves, label, marker
Material: smart screen
Copyright © Huawei Digital Power Technologies Co., Ltd.
5 Parts Replacement
108

Advertisement

Table of Contents
loading

This manual is also suitable for:

V100r022c10

Table of Contents