The listed tools are for routine maintenance only. Prepare other tools as required.
2.2 Reference Documentation
The documents provided in the solution only include the special maintenance
items, maintenance methods, and precautions of the components. For other
maintenance items of the components, see the documents delivered with the
components.
Table 2-2 Maintenance documents to be prepared
Component
Integrated UPS
NetCol5000-A025 In-row Air
Cooled Smart Cooling Product
ECC800-Pro
NetEco
2.3 Pre-fab. Module Entry and Working Requirements
The following table describes the requirements for working in the FusionDC1000.
Item
Before entry
Issue 01 (2021-04-20)
NO TE
NO TICE
NO TE
● The ECC800-Pro/NetEco version depends on the version in use. Click
ECC800-Pro/NetEco WebUI to obtain the current version.
● For NetEco maintenance, see the NetEco documents.
Requirement
● Obtain the entry permit.
● Perform detailed operations based on the requirements
specified by the manager of the FusionDC1000.
Copyright © Huawei Technologies Co., Ltd.
2 Operation and Maintenance Preparations
Document
UPS5000-E-(50 kVA–125 kVA) User Manual
(Integrated UPS 3.0)
NetCol5000-A025 In-row Air Cooled Smart
Cooling Product User Manual (300 mm
Width))
ECC800 Data Center Controller V100R21C00
User Manual (for ECC800-Pro)
iManager NetEco Product Documentation-
(V600R021C00)
on the