Huawei FusionDC1000A Maintenance Manual page 69

Prefabricated all-in-one data center
Hide thumbs Also See for FusionDC1000A:
Table of Contents

Advertisement

FusionDC1000A Prefabricated All-in-One Data
Center
Maintenance Guide (IT Scenario)
Step 5 Remove the front and rear sealing plates from the smart cooling product base.
Figure 4-4 Removing sealing plates from the smart cooling product base
Step 6 Reinstall the removed ESD floors.
● The ventilation floor panel of the hot aisle can be reinstalled after the water
refill and drainage pipes of the smart cooling product are removed.
● Adjust the height of the floor tray to ensure that the reinstalled floor panels are
flush with other floor panels.
Step 7 Remove fasteners at the top and bottom of the smart cooling product.