Backup
Back-up the system loop address allocation data to the memory.
Regularly back-up the configuration data during
commissioning, do this every 15 minutes to ensure the
changes made to the configuration is not lost.
Loop wiring tests
Carry out tests on each loop wiring by introducing open and short
circuit wiring faults. Ensure the panel provides an indication of each
fault. Run the '
Repair
' function at the panel after each wiring fault removal.
Audio loop wiring tests
Connect each audio loop and carry out tests to ensure live and
auxiliary messages are outputted to the DAU speaker circuits.
Background music and PA microphone
– Connect and test Background music system
– Connect and test PA microphone
– Test the emergency microphone.
Devices set up
Ensure all devices on the loop circuits are correctly set up.
– Calibrate speaker circuits on micro DAUs
– Adjust volume of audio at each micro DAU and
Mains Powered DAU.
Retrieve the system data to Commissioning tool
Connect the commissioning tool and retrieve the system data,
see Commissioning tools manual.
4188-856_issue 7_07/15_Generic Vigilon (Compact + VA) Comms.
Vigilon 4/6 loops & Compact (VA) panels & network nodes
Configure the system using the Commissioning Tool
Configure the system to site specific requirement using the
Commissioning tool.
Transmit the configured system to the panel
Connect the commissioning tool to the panel and transmit the
system configuration.
Beam Sensor alignment
If there are beam sensors on the loop then commission the beam
sensor pair using the alignment and autogain function at the panel.
Installed system test
Put the panel in test mode and then carry out tests in accordance with
the recommendations of BS5839:Part 1 and also in accordance
with project requirements:
– Interface units
Prior to
carrying out
functional test on external equipment connected
to the I/O circuits, ensure the I/O circuits remain isolated.
After functional tests, reconnect the I/O circuits and where appropriate
test the I/O circuits to project recommendations.
– Fire sensors
Ensure a device fire causes alarms in the system to sound in
accordance with site specific requirement.
S-Cubed - The output volume of an S-Cubed can be adjusted using:
[Set up] ->[Setup]-> [Device]-> [Loop]->[S-Cubed]->[Volume] and then
enter a value between 16 min to 100 max. command at the panel.
Repeat and Mimic panels
Check events are displayed and indicated
– Connect Master alarm and Monitored input circuits and move the
end-of-line resistor to the end of each circuit.
– Sounders - Conduct sound level tests to ensure the levels do not fall
below the requirements.
– VAD / Strobe - Check the appropriate S-Quad and S-Cubed devices
provide the visual alarm.
– Messages - Check the correct messages are announced from the
Speakers, S-Cubed and S-Quad devices where installed.
– Remove the Test mode and ensure any disablements are re-enabled.