Chapter 5 Installation
Tower installation
When installing the UPS unit's power module, pay attention to any connectors on the
Attention!
back side of the UPS unit such as RPO and ROO, serial connectors etc. Make sure that
these are not getting damaged!
When installing a UPS unit and any additional EBMs as a tower do not leave any gaps
between any module! This means that any modules must be mounted adjacent to each
other! See also the
installation. This also applies to the tower installation of the UPS units.
Leaving gaps between modules can damage the UPS and any interconnection cables! This
can lead to the UPS unit malfunctioning!
Note that the thick power cables running between the UPS power module and any EBM
carries a high electrical current of a couple of Ampères!
Any damage caused by incorrect physical installation and the subsequent repair work is
not covered by UPS warranty or maintenance contract.
To install the unit in a tower configuration:
Step 1. Place the UPS on a flat, stable surface in its final location.
Step 2. Always keep 150 mm of free space behind the UPS rear panel.
Step 3. If installing additional units, place them next to the UPS in their final location.
56
images
in
Chapter 5 Installation
/
Rack Installation
6U Rack or Tower UPS RT8kVA and RT11kVA IUOMG
for correct UPS