Lenovo 5594-8KX User, Installation And Maintenance Manual page 159

6u rack or tower ups rt 8.0 kva and rt 11.0 kva and maintenance bypass
Hide thumbs Also See for 5594-8KX:
Table of Contents

Advertisement

Chapter 10 UPS maintenance
Running a battery test
Automatic battery tests are done every week in automatic charging mode and at each cycle in
Advanced Battery Management (ABM) mode. The frequency of the tests can be modified using
the LCD panel. See
Note: Make sure that the Battery mode is not displayed and the battery low alarm does not activate
during a battery test.
The automatic discharge test is enabled by default and runs during the transition from
mode. After the test is complete, the charge cycle restarts to completely charge the
Rest
batteries and then continues to
The automatic battery test runs approximately once every three months and does not run
again until the next test period. If a manual battery test is requested, the automatic battery test
timer is reset so that it does not run for the next test period.
Requirements for successful battery test
In order for a battery test to complete successfully the following minimum requirements must
be met:
1. Load must be at last 10% of the rated capacity or greater to run adequate discharge,
however 25% is recommended load capacity of the UPS that should be protected by the
UPS unit
2. Battery capacity should be  80 %, that is the battery is charged to at least 80 % of its
capacity
3. There is no running alarm (except Battery fault)
4. Load level has not varied by more than +/-10 % (from the initial load level present at the
beginning of the test to the end of the test)
5. The bypass voltage is in tolerance for bypass transfer (in case of end of backup, to
transfer to bypass)
6. UPS mode must be in Online mode or HE (High efficiency) mode.
These requirements applies to both the UPS itself and any attached EBM(s), that is for all
battery packs present in the UPS installation.
UPS can either be in ABM or continuous battery charge mode.
Additional information
For both the automatically and manually started battery tests, the following applies:
6U Rack or Tower UPS RT8kVA and RT11kVA IUOMG
User settings
in
Chapter 3
mode.
Rest
for more details.
to
Float
131

Advertisement

Table of Contents
loading

This manual is also suitable for:

5594-8px5594-9kx5594-9px

Table of Contents