Step 5 Set CIM parameters.
Parameter
Parallel
Configuration
Current source or
Current acquisition
source
Battery N line
Multi-Hall cur.
setting
Total battery
capacity
Batt. installation
time
BIM Number of
CIM
Batt. String Qty. or
Number of battery
strings
Issue 07 (2019-01-02)
V289B003 and earlier versions
a.
On the CIM WebUI home page, choose Monitoring > CIM System > Running
Parameter, and set Parallel Configuration and Basic Information.
b.
On the CIM WebUI home page, choose System Settings > Batt. String Config,
and set Batt. String Config.
Description
This parameter needs to be set when multiple CIMs are connected in
parallel and does not need to be set when there is only one CIM. Set
Parallel Configuration to Parallel, and set CIM parallel qty..
Configure IP addresses for multiple CIMs.
The actual specifications of the Hall effect sensor prevail.
Set whether there is a battery N wire according to the actual
situation.
The number of positive or negative Hall effect sensors in a single
battery string and should be greater than or equal to 1.
Time when the battery is installed for the first time. Does not need
to be reset when part of batteries are replaced.
Indicates the total number of BIMs managed by the CIM.
The number of battery strings managed by the CIM.
Copyright © Huawei Technologies Co., Ltd.
One iBOX: Capacity of one battery string x Number of battery
strings connected in parallel.
N iBOXs connected in parallel: Capacity of one battery string x
(Number of battery strings managed by iBOX 1 + ... + Number
of battery strings managed by iBOX N).