Figure 3-2 BIM installation position
Procedure
Step 1 Install a BIM.
Issue 07 (2019-01-02)
In the figure, the circuit breaker panel of the battery cabinet has been removed. Before
removing the circuit breaker panel, knock off the cover on the CIM indicator hole on the
panel.
If battery cabinets are combined, remove the side panels between the battery cabinets.
If the battery string is configured with the neutral wire, measure the currents of the
positive and negative battery string cables. If the battery string is not configured with the
neutral wire, measure the current of either the positive or negative battery string cable.
The following uses the scenario where the battery string is configured with the neutral
wire as an example.
The battery appearance is for reference only.