Fix the pedestal to the drive frame in reverse order to step Remove the pedestal :
1. Fix the fastening screws.
WARNING! The fixing is important because the screws are required for the grounding of the
drive.
2. Connect the terminals at the top of the pedestal to the terminals at the bottom of the upper part of
the drive frame.
WARNING! Be careful not to drop screws inside the pedestal. Loose metal pieces inside the
unit may cause damage.
3. Tighten the connections.
View of frame size R7
1
2
R8: Fasten the OMIO board in reverse order to step Remove the pedestal .
Fasten the drive frame to the wall (recommended):
Fasten unit with screws or bolts to the holes in the wall.
Connect the control cables as described in section
Fasten the covers:
1. Connect the control panel cables. See step Remove the Pedestal .
2. Fasten the upper front cover.
3. R7: Fasten the roof.
4. Fasten the lower front cover.
Terminal connection screws
R7: M8 (5/16 in.) combi screws
Tightening torque: 15...22 Nm (0.59...0.87 lbf ft)
R8: M10 (3/8 in.) combi screws
Tightening torque: 30...44 Nm (22...32 lbf ft)
1
Connecting the Control Cables
33
on page 35.
Installation

Advertisement

Table of Contents
loading

This manual is also suitable for:

Acs550-u2Acs550-01Acs550-u1

Table of Contents