Figure 7-2 Fully weld along the joints.
Step 5 After the welding is complete, polish the welding joints. Use water to check for
leakage.
Figure 7-3 polish the welding joints
Step 6 Clean the welding joints with alcohol, and add the paint (epoxy zinc rich primer
+epoxy intermediate paint+polyurethane topcoat) according to the procedure:
After the primer is dry, apply the epoxy intermediate paint. After the intermediate
paint is dry, apply the polyurethane topcoat.
----End