Grounding Containers - Huawei FusionModule1000A20 Installation Manual

It solution
Hide thumbs Also See for FusionModule1000A20:
Table of Contents

Advertisement

FusionModule1000A20 IT Solution
Installation Guide (2016.05, AI Version)
Figure 5-8 Tightening the twistlock in a single-capacity base
----End
Installation Verification
After containers are installed, verify the installation to ensure normal use of products and
smooth subsequent installation.
Table 5-2 Installation checklist
No.
1
2
3

5.3 Grounding Containers

Prerequisites
Preparations
Tool: torque wrench
Issue 02 (2017-01-10)
Check Item
Bolts and nuts
Contact between
containers and bases
Container doors
Containers have been installed.
The grounding positions have been specified.
The grounding requirements have been specified.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Check Method
Partially tighten them
using a wrench.
Observe.
Open container doors.
5 Installing a Container
Check Standard
Bolts and nuts are tightened.
A container is in close
contact with and evenly
supported by the bases
underneath.
All container doors can be
smoothly opened and closed.
22