Periodical Inspection - Toshiba TOSVERT VF-S9 Instruction Manual

Compact inverter 1-phase 200v class 0.2 2.2kw 3-phase 200v class 0.2 15kw 3-phase 400v class 0.75 15kw
Hide thumbs Also See for TOSVERT VF-S9:
Table of Contents

Advertisement

Check points
1. Something unusual in the installation environment
2. Something unusual in the cooling system
3. Unusual vibration or noise
4. Overheating or discoloration
5. Unusual odor
6. Unusual motor vibration, noise or overheating

14.2 Periodical inspection

Make a periodical inspection at intervals of 3 or 6 months depending on the operating conditions.
Mandatory
Prohibited
Check items
1. Check to see if all screwed terminals are tightened firmly. If any screw is found loose, tighten it again
2. Check to see if all crimped terminals are fixed properly. Check them visually to see that there is no trace
3. Check visually all cables and wires for damage.
4. With a vacuum cleaner, remove dirt and dust, especially from the vents and the printed circuit boards.
5. When leaving the inverter unused for a long time, check it for functioning once every 2 years or so by
6. If the need arises, conduct an insulation test on the main circuit terminal board only, using a 500V insu-
14
• Before inspection, perform the following steps.
(1) Shut off all input power to the inverter.
(2) Wait for at least ten minutes and check that the charge lamp is no longer lit.
(3) Use a tester that can measure DC voltages (800V DC or more), and check that the voltage to the
DC main circuits (across PA-PC) does not exceed 45V.
Performing an inspection without carrying out these steps first could lead to electric shock.
• Never replace any part. This could be a cause of electric shock, fire or bodily injury. To replace parts,
call the local sales agency.
with a screwdriver.
of overheating around any of them.
Always keep them clean to prevent an accident due to dirt or dust.
supplying it with electricity for at least 5 hours with the motor disconnected. It is advisable not to supply
the commercial power directly to the inverter but to gradually increase the power supply voltage with a
transformer.
lation tester. Never conduct an insulation test on control terminals other than terminals on the printed
circuit board or on control terminals. When testing the motor for insulation performance, separate it from
the inverter in advance by disconnecting the cables from the inverter output terminals U, V and W.
When conducting an insulation test on peripheral circuits other than the motor circuit, disconnect all ca-
bles from the inverter so that no voltage is applied to the inverter during the test.
Danger
N-2
E6580757