Figure 6-59 Connecting cables to a power connector (BOM number: 14190892)
Figure 6-60 Connecting cables to a power connector (BOM number: 14190242)
Step 9 Secure the pad power connector holder.
1.
2.
Issue 05 (2020-03-25)
Remove the baffle plate from the power connector mounting holes in the door box.
Secure the pad power connector holder to the door box using two M4x12 screw
assemblies.