Huawei V500R003C00 Maintenance Manual page 101

Smart modular data center
Table of Contents

Advertisement

FusionModule2000 Smart Modular Data Center
Maintenance Guide
Preparations
Procedure
Step 1 Label each cable based on the corresponding ports on the rack environment unit.
Step 2 Disconnect cables from the rack environment unit.
Step 3 Remove the screws from the mounting ears on both sides of the rack environment unit and
remove the old rack environment unit.
Figure 6-48 Removing the rack environment unit
Step 4 Secure the reserved rack environment unit in the original position using four screws.
Step 5 Connect cables to the reserved rack environment unit based on the cable labels.
Step 6 Synchronize the parameters of the rack environment unit on the ECC800-Pro WebUI.
Step 7 On the ECC800-Pro WebUI, choose Monitoring > System > ECC800 > Controls > Delete
device with communication failure, and click Submit.
Step 8 Log in to the ECC800-Pro WebUI, and check the parameters and communication status of the
rack environment unit to ensure normal communication.
----End
Issue 05 (2020-03-25)
Tools: Phillips screwdriver, labels, marker
Material: rack environment unit
Copyright © Huawei Technologies Co., Ltd.
6 Parts Replacement
94