4.4 Commissioning Devices

Checking Cable Connections and Powering On the ECC500
Check that power cables, ground cables, RS485 communications cables, and AI/DI signal
cables are connected to the main control module, RS485 expansion card, AI/DI expansion
card, and Independent Deployment AI/DI Unit in the manner specified in
Cables. Connect the external power supply to the power module to power on the ECC500.
Checking Indicator Status
Check the indicators on the main control module, RS485 expansion card, AI/DI expansion
card, and Independent Deployment AI/DI Unit.
Table 4-1 Indicator description
Module
Main control
module
RS485 expansion
card, AI/DI
expansion card, and
Independent
Deployment AI/DI
Unit
Setting ECC500 Communications Parameters (LCD)
Table 4-2
Table 4-2 Communications parameters
Parameter
IP address
Subnet mask
Gateway
Figure 4-20
Issue 05 (2020-03-16)
Normal Indicator Status
lists the communications parameters that can be set over the LCD.
Description
Set to 192.168.1.168 by default but can be adjusted according to the
network plan.
Set to 255.255.255.0 by default but can be adjusted according to the
network plan.
Set to 192.168.1.1 by default but can be adjusted according to the
network plan.
shows the procedure for setting these communications parameters.
Change the password after your first login.
Copyright © Huawei Technologies Co., Ltd.
Table 4-1
The run indicator blinks (on for 1s and then off for 1s).
The alarm indicator is off.
The PWR indicator is steady on.
The RUN indicator blinks (on for 1s and then off for 1s).
The ALM indicator is off.
4 Installation and Commissioning
4.3.5 Connecting
describes their normal status.
42

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents