(1) 3 mm thick steel plate
4.
This step requires two persons working together, one pushing the air conditioner from behind
and the other pulling the air conditioner at the front.
Issue 01 (2019-03-05)
Figure 4-29 Placing the steel plate and pipe
Push the air conditioner at the back towards the cold aisle at the front. Verify that the air
conditioner front bottom will be on the steel pipe placed in
conditioner is pushed about 100 mm away from the base.
Copyright © Huawei Technologies Co., Ltd.
(2) 1.5 m long DN32 steel pipe
Step 13.3
4 Parts Replacement
after the air