Cut a pipe inside the air conditioner about 20 mm away from a turning point in the vertical
direction.
Cut a pipe outside the air conditioner about 40 mm away from the air conditioner base on
the vertical direction.
(1) Cutting points on air conditioner pipes
Step 13 Move the air conditioner.
Steel plates and pipes must be placed a certain distance away from the pre-fab. module side
wall to prevent scratching the side wall.
1.
2.
3.
Issue 01 (2019-03-05)
Figure 4-28 Cutting air conditioner pipes
Take the fittings for moving the air conditioner from the pre-fab. module fitting bag.
Fittings for moving an air conditioner include a 3 mm thick steel plate, two 1.5 m long DN32 steel pipes,
and three 0.5 m long DN32 steel pipes.
Place the 3 mm thick steel plate on the raised floor in the cold aisle.
Place one 1.5 m long DN32 steel pipe above the 3 mm thick steel plate about 100 mm
away from the base of air conditioner D1.