Procedure
Step 1 Switch off the active and standby power supplies to the fire alarm control panel.
Step 2 Hold the heat detector, and rotate it counterclockwise to remove it from the base.
Figure 4-64 Removing a heat detector
Step 3 Remove cables from the base using a Phillips screwdriver.
Step 4 Remove the screws on the base using a Phillips screwdriver, and remove the base.
Step 5 Install the new base to the same position, and reconnect the cables.
Step 6 Hold the new heat detector body, align the heat detector indicator with the position shown by
(1) in Figure 4-65, and turn the detector body clockwise to the position shown by (2) in Figure
4-65 to install the heat detector.
Issue 01 (2019-03-05)
For the diagrams, see the initial configuration parameter manual for the solution in use.
Before replacing the heat detector, inform the related administration department of the
temporary downtime of the fire control system. After the replacement, inform the
administration department that the system has become operational.
As a terminal resistor is connected to the last heat detector in the loop in parallel, remove the terminal
resistor from the faulty heat detector, and connect the resistor to the new heat detector when you replace
the heat detector.
Copyright © Huawei Technologies Co., Ltd.
4 Parts Replacement
123

Advertisement

Table of Contents
loading

Table of Contents