Follow-up Procedure
Dispose of the removed BIM that is confirmed faulty.

4.1.10 Replacing the Power PDB

Prerequisites
A spare power PDB of the same model is available and functional.
Impact on the System
None
Preparations
Tools: Phillips screwdriver, socket wrench
Materials: spare power PDB
Documents: power supply and distribution system diagram
Skill requirement: electrician's work permit
Procedure
Step 1 Power off the power PDB based on the power supply and distribution system diagram.
Step 2 Remove cables using a socket wrench and Phillips screwdriver.
Step 3 Remove screws securing the power PDB and remove the power PDB.
Step 4 Secure the new power PDB and connect cables correctly.
----End
Follow-up Procedure
Dispose of the removed power PDB that is confirmed faulty.
Issue 01 (2019-03-05)
The internal resistance can be measured only when the batteries are fully charged, and no alarm is
generated in the intelligent monitoring system. A measurement can be performed at least 45 minutes
after the previous measurement ends. The battery internal resistance will change to an invalid value
after power-off and then power-on again. By default, the BIM checks the battery internal resistance
once every 24 hours as instructed by the CIM. The red BIM indicator is steady on during the check.
You can also measure the battery internal resistance manually.
On the home screen of the CIM WebUI, choose Monitoring > CIM System > Running Control,
click Internal resistance, select a battery number, and click Submit to measure the internal
resistance of the battery.
For the diagrams, see the initial configuration parameter manual for the solution in use.