Figure 6-58 Connecting cables to a power connector (BOM number: 14190242)
Step 9 Secure the pad power connector holder.
1.
2.
Figure 6-59 Securing a pad power connector holder
Step 10 Reinstall the charging cable for the power connector.
Step 11 Reinstall the baffle plate under the power connector.
----End
Issue 03 (2019-12-04)
Remove the baffle plate from the power connector mounting holes in the door box.
Secure the pad power connector holder to the door box using two M4x12 screw