AQ25A SERIES PROGRAMMABLE BOILER CONTROL PANELS
be copied to the AQ25A's CURRENT settings and the
Control Panel begins to operate with these values
immediately.
• SETUP settings are the specific settings for this installation
which an installer has saved after the AQ25A is set up and
operating well. These are saved for future recall, in case the
system's settings are inadvertently changed.
— To save this installation's settings for the first time, go to
the EQUIPMENT SETUP > SAVE/RESTORE sub-
menu. Position the indicator arrow (←) beside SAVE
SETUP and press OK. This saves the current system
settings to the SETUP values.
— To retrieve the SETUP values at any time in the future,
go to the EQUIPMENT SETUP > SAVE/RESTORE
sub-menu and select RESTORE SETUP to load those
values into the AQ25A as the CURRENT settings. The
system will now operate according to these retrieved
settings.
— If the current settings are modified after a RESTORE
SETUP operation is performed, simply select SAVE
SETUP again to overwrite these new settings into the
SAVE settings memory.
CAUTION
If you change any system settings after a
RESTORE SETUP operation, you change the
current settings that the AQ25A uses as its basis of
operation.

TROUBLESHOOTING

The following information helps the installer correctly identify
system problems, making troubleshooting much faster.
Table 3 and Table 4, beginning on page 21, describe the
possible error codes and status notices that can be
communicated on the AQ155 / AQ157 Zoning Modules'
diagnostic LEDs.
System Status Information
To aid in troubleshooting hydronic systems controlled by an
AQ25A, the operational status of the system is shown on the
System Status page. Status notices and error messages
display here as appropriate, i.e., only those that are pertinent
to the system's current operation will be displayed. See Table 4
on page 21 for a complete list of status notices and error
messages. The System Status page is available from the User
Menu.
When a new AQ2000 component is connected on the
AQUATROL network, its settings are communicated to the
AQ25A Control Module within 10 seconds of being connected.
If the component is an AQ1000 thermostat, the setpoints for
that zone thermostat can be modified from the AQ25A Control
Module as soon as it is recognized.
When an AQ1000 thermostat is disconnected from the
AQUATROL network, a message displays on the System
Status page of the AQ25A indicating "Lost Zone A-xx", where
"xx" is the specific identity, or address, of the lost zone. This
helps the servicing contractor quickly identify the lost zone and
fix its wiring to re-establish communication with the AQ25A
Control Module.
69-2119—02
This diagnostic information is very valuable and the System
Status page is the first place a contractor should look for
information when troubleshooting system problems.
Communications Loss
Because all AQ2000 Series components communicate with
each other via the dedicated AQUATROL network when
controlling a hydronic system, one possible failure mode of the
AQ25A would be loss of communication between the AQ15A
Control Module and any connected Zoning Modules, or
between a Zoning Module and any zone thermostats
connected to the AQUATROL network. In general, the Control
Module:
• Periodically tries to re-establish communication with any
lost components on the network.
• Initializes any component that re-establishes its
communication.
• Displays an error code on the AQ25A's System Status
page, until the error is corrected and/or communication is
re-established.
Control Module Reaction
When the AQ15A Control Module loses communication with
any number of zones for more than one minute (as long as
there's still at least one zone communicating on the
AQUATROL network), the AQ25A continues to deliver heat to
the other non-communicating zones and the address of each
lost zone (e.g., A-7, B-4) displays on the System Status page.
When communication is lost with all zones, the AQ25A enters
BOILER FREEZE PROTECTION mode, in which it fires the
boiler and then activates the Boiler (supply) pump and zone
equipment for a period of 10 minutes every hour. This should
provide sufficient heat to the system to prevent a building from
freezing up until communication is re-established between the
AQ2000 Series components.
BOILER FREEZE PROTECTION mode is disabled when the
outdoor temperature is above the warm weather shutdown
(WWSD) temperature setting.
Zoning Module Reaction
When a Zoning Module loses communication with the Control
Module (as long as there is at least one other Zoning Module
communicating with the Control Module), the Zoning Module
operates its pumps or valves in a conventional, non-
synchronized zoning fashion. That is, it operates according to
the demands from the thermostats, without zone
synchronization or waiting for permission from the AQ15A
Control Module to operate. This allows the zones to extract any
heat provided by the boiler.
When using AQ1000 thermostats and communication is lost
between a Zoning Module and any of its thermostats, that zone
enters Single Zone Freeze Protection mode. In this mode, the
zoning equipment is operated for an amount of time equal to
one-half of the maximum demand of all other zones on the
network. This helps prevent the lost zone from freezing. This is
especially helpful if a zone's thermostat is removed from the
wall while a room is being painted. When used with 2-stage
thermostat operation, only the first stage will be activated in the
freeze protection mode.
When using digital, non-communicating thermostats other than
the AQ1000, the Single Zone Freeze Protection is disabled for
those zones.