5.10.3
Installing IP54 roof-mounted cooling units
One by one, install the IP54 roof-mounted cooling units on top of the PCU
compartments that have the designated openings.
Item
Self-tapping Torx screws
Washers with sealing
Tube spacers
1. Align the water inlet / outlet (1), drain outlet (2), and cables (3) of the
unit with the designated openings in the cabinet roof.
2. Slowly lower the cooling unit onto the cabinet.
Make sure that the water inlet / outlet, the drain outlet, the cables and
the screw holes fit.
3. Screw the cooling unit to the cabinet roof.
4. To get to the water inlet / outlet and the drain outlet from inside
the cabinet.
• Try to reach them from underneath the cable duct at the front
• Remove the back wall if necessary to reach them from the back.
3BHS799208 E01 REV E
Table 5-3 Installation material per IP54 unit
Quantity
22
22
2
ACS5000 WATER-COOLED USER MANUAL
05 MECHANICAL INSTALLATION
Details
M6x16
6.8x1 (4.8x2.8)
2
3
1
82/186