Figure 3-28 Connecting the cable between the iBOX and the LAN switch
Step 2 (Optional) If multiple iBOXs are connected in parallel, connect each iBOX to the LAN switch
independently.
----End

3.7 Installation Verification

Table 3-7 Installation checklist
No.
1
2
3
4
5
Issue 07 (2019-12-30)
Check Item
Installation of devices in the
iBattery system
Labels of cables to the POE port,
COM port, BCB port, and HALL
current detecting port on the
iBattery system
Connections of cables to the
POE port, COM port, BCB port,
and HALL current detecting port
on the iBattery system
iBOX DIP switch
Positive and negative iBAT input
power cables
Copyright © Huawei Technologies Co., Ltd.
Acceptance Criteria
All devices in the iBattery system are
installed properly and reliably.
Cables to the iBattery system have been
connected correctly. Both ends of each cable
are labeled. Labels are clean and correct, and
provide concise and understandable
description.
Cables to the iBattery system have been
connected securely and reliably. For the
cables secured by screws, the spring washers
are flattened. All cable connections are
secure. No open circuits and potential risks
exist on cable connections.
All DIP switches on iBOXs are correctly set.
Use a multimeter to check that the voltage
between the positive and negative iBAT input
power cables is correct.