Install the Cisco Catalyst 8300 Series Edge uCPE
Figure 20: Grounding the Chassis
1
2
These are the steps to install the ground connection for the device. The ground lug kit is provided with the
chassis:
Before you begin
• Connect the chassis to the earth ground; the ground wire must be installed in accordance with local
• For grounding, use size 14 AWG copper wire and the ground lug provided in the accessory kit.
1. Strip one end of the ground wire to the length required for the groundlug.
2. Crimp the ground wire to the ground lug using a crimp tool of the appropriatesize (7/8 inches strip length).
3. Attach the ground lug to the chassis as shown in the figure. Use the screws provided and with the ground
lug to attach the lug to the device.

Initial Server Setup

Local Connection Procedure
• Ensure that the device is powered on.
• Connect serial console port on the front panel of the device.
• When you see the prompt, you can press F2 to get into the setup (BIOS) to change some settings.
• After you have performed the required configuration, save the setup and continue to boot.
electrical safety standards.
Ground lug
Screws
Cisco Catalyst 8300 Series Edge uCPE Hardware Installation Guide
Initial Server Setup
29