7. Ensure the hex nut on the rear retaining bracket is tight. The following image shows the server and
rear retaining bracket correctly installed.
8. If you are using the 8-port KVM switch/control console for your human interface (pre-installed in the
Honeywell factory), connect the KVM cable mouse and keyboard connections to the USB
connectors on the rear of the server. The KVM cable may have separate USB connections for the
mouse and keyboard or they may be combined into one USB connector through a USB to PS/2
adapter (included with the KVM cable).
3.4.3
Installing the server using the slide tray mounting kit model TP-
SPCMS1
This procedure is the same regardless of whether the cabinet is 800 or 1000 mm deep. Do NOT remove
the plastic feet from the bottom of the server (when oriented as a tower). This installation procedure
intentionally omits use of the server front bezel cover. This is done to allow the front retaining brackets
to bear against a flat surface. If the server front bezel is required for security reasons, the front retaining
brackets bears against an angled surface which may reduce their effectiveness.
To install the server
1. From the front of the cabinet, open the door to access the pre-installed fixed rail mounting kit.
2. Remove the left and right front retaining brackets.
3. Using the handle on the front of the slide tray, pull it forward until the tray locks into its fully