Appendix A - Installing RTP

Using an RTP to field wiring the 16 Point DC DI

To wire the 16 Point AC DI using an RTP
1. Mount the RTP cable assembly to ControlEdge 900 Controller. See the
202
ATTENTION:
RTP and cables are intended for permanent installation within their own
l
enclosure.
The RTP combines the two groups of 8 inputs into one group of 16.
l
following figure for the example installation diagram.
a. Remove the relevant key tabs from the terminal block to allow connection
with the module.
b. Connect the appropriate cable to the module at ControlEdge 900
Controller. Possible options are:
900RTC-L210 Remote Termination High Voltage Cable Assembly, 1.0
l
meters long