GE Multilin D20E Installation And Maintenance Manual page 99

Ethernet i/o module
Table of Contents

Advertisement

Power up procedure
Test your field I/O
102
To power up and test the D20E module:
1.
Turn on the Substation Controller or Computer.
2.
Turn on the power source to the D20E module.
3.
Verify that the D20E module LEDs indicate normal operation, as follows:
Label
Color
DC1
Blue
DC2
Blue
ON
Red
RUN
Red
For information on the operation of all LED indicators, see chapter:
Module
on page 103.
Test your D20E module inputs or outputs, as appropriate for your substation automation
system.
Refer to the manual for your substation automation system. For example:
D400 Substation Gateway Instruction Manual (994-0089)
D20MX Substation Controller Instruction Manual (994-0140)
For information on the operation of all LED indicators, see chapter:
on page 103.
To test previously configured input/output points using DAPserver Studio:
1.
Go to the Device menu > Explore tab view.
2.
Click on the desired PROVIDERS device name.
3.
Click on the Device icon in the upper-left of the main window.
4.
Click on one of the following input/output types on the left side of the main window
pane under Health:
Digital Input
Digital Output
Analog Input
Counter
5.
Verify the D20E module operation of inputs or outputs by sending a DO command or
reading the status of a DI and AI point through DAPserver Studio > Explorer.
GE INFORMATION
CHAPTER 8: POWERING-UP AND TESTING A D20E MODULE
Normal operation
On solid when power supply 1 input is present
On solid when power supply 2 input is present
On solid when D20E module power supply output is present
CPU is operating properly, 1sec ON/OFF after restart initialization
D20E ETHERNET I/O MODULE INSTRUCTION MANUAL
Using the D20E
Using the D20E Module

Advertisement

Table of Contents
loading

Table of Contents