CHAPTER 6: PRELIMINARY POWER UP AND TEST
Power supply requirements
Preliminary power-up and test procedure
D20E ETHERNET I/O MODULE INSTRUCTION MANUAL
If you did not order a GE Grid Solutions power supply (see
D20E Power Supply), and instead are obtaining a non-GE power supply, ensure that you
purchase a power supply unit that is:
•
Certified for use in the country of the installation
•
Includes double insulation or reinforced insulation
•
Supports overvoltage category II
Ensure that the power supply cable used is:
•
No longer than 10 m (32.8 ft)
•
Not run in parallel with a noise source
To verify the previous installation tasks have been successfully completed:
1.
Power up the D20E device.
2.
Login to a DAPserver Studio session.
3.
Verify the firmware version:
3.1.
Open DAPserver Studio.
3.2.
From the Device menu, click Explore > System > Health > Item 24 > FMWVER.
4.
Confirm that:
–
The correct firmware and configuration are loaded on the D20E device.
–
All communication, network and power connections have been properly
connected.
Ordering guides
GE INFORMATION
on page 23 >
85