Installing The Equipotential Cable And Pgnd Cable - Huawei DBS3900 Installation Manual

Icr dual-mode base station
Hide thumbs Also See for DBS3900:
Table of Contents

Advertisement

DBS3900 (ICR)
Installation Guide
12
Installing the Equipotential Cable and
This chapter describes the procedures for installing the equipotential cable and PGND cable.
Prerequisites
A PGND cable and an equipotential cable need to be prepared onsite.
specifications of a PGND cable and an equipotential cable.
Table 12-1 Cable specifications
Cable
PGND cable
Equipotential
cable between the
IFS06 and the
IMB03
Equipotential
cable between the
upper and lower
IMB03s
Procedure
Step 1 Cut the cable to a length suitable for the actual cable route.
Step 2 Add an OT terminal to each end of the cable according to the instructions in Assembling the OT
Terminal and the Power Cable.
Step 3 Install the PGND cable and equipotential cable, as shown in
Issue 12 (2015-04-30)
Connector at One End Connector at the
OT terminal (M8)
OT terminal (M6)
OT terminal (M4)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.

12 Installing the Equipotential Cable and PGND Cable

PGND Cable
Other End
Depending on the
external ground bar
OT terminal (M6)
OT terminal (M4)
Figure
Table 12-1
lists the
Cross-Sectional Area
of the Cable
2
2
16 mm
(0.025 in.
)
2
2
16 mm
(0.025 in.
)
2
2
6 mm
(0.009 in.
)
12-1.
88

Hide quick links:

Advertisement