Loading System MkII
If using Precast Kentledge as the ballast option, please proceed
to step 3. If using cast concrete as the ballast option, please
proceed to step 4 and if using gravel as the ballast option, please
proceed to step 5.
3. Precast Kentledge ballast option
Check that the two rear Corner Posts are inserted correctly,
and the two front Corner Posts are left aside. Use a forklift
truck to place two 800 kg COMBISAFE Precast Kentledge
onto the Bottom Frame, see Figure 16. When the concrete
blocks are in place, place the two remaining Corner Posts into
the Bottom Frame. Next step is to mount the top unit, please
proceed to step 6.
4. Cast-In-Concrete ballast option
4.1. Check that all four Corner Posts are inserted correctly into
the Bottom Frame. Cut a piece of 18 mm Formwork Ply-
wood, complying with EN 636-3, in the format as shown in
Figure 17 and place in the centre of the Bottom Frame. Bolt
the eight Formwork Supports to the welding nuts located on
the Corner Posts. Use the bolts attached to the Formwork
Supports, see Figure 18. At this step it is not necessary to
tighten the bolts.