Toro Sand Pro 5040 Service Manual page 51

Hide thumbs Also See for Sand Pro 5040:
Table of Contents

Advertisement

Procedure for Charge Pressure and Implement Re-
lief Valve (R1) Pressure Tests:
1. Make sure hydraulic oil is at normal operating tem-
perature by operating the machine for approximately 10
minutes.
2. Park machine on a level surface with the attachment
lowered. Make sure engine is off and that the parking
brake is applied.
3. Read and follow Precautions for Hydraulic Testing.
IMPORTANT: Make sure to thoroughly clean around
all hydraulic connections that will be disassembled.
4. Install pressure gauge to machine:
A. For Sand Pro 3040 and Infield Pro 3040 ma-
chines, remove plug from one of the hydrostat
charge test ports (Fig. 17). Install pressure gauge to
test port.
B. For Sand Pro 5040 and Infield Pro 5040 ma-
chines, install a tee connector with pressure gauge in
series between the tee fitting on the lower right side
of the hydrostat and the hydraulic hose from the hy-
drostat (Fig. 18).
5. Make sure that traction pedal and lift control lever are
in neutral and the parking brake is applied.
6. Start engine and run at low idle speed. Check for hy-
draulic leakage and correct before proceeding with test.
7. Operate engine at full speed (3400 RPM). Verify
pump hub speed with a phototac.
8. The pressure gauge will display system charge pres-
sure and should read as follows. Record test results.
A. For Sand Pro 3040 and Infield Pro 3040 ma-
chines, charge pressure should be from 120 to 330
PSI (8.3 to 22.7 bar).
B. For Sand Pro 5040 and Infield Pro 5040 ma-
chines, charge pressure should be from 70 to 330
PSI (4.8 to 22.7 bar).
NOTE: If machine is equipped with optional front lift,
charge pressure will increase approximately 50 PSI
(3.5 bar).
IMPORTANT: DO NOT hold system at implement re-
lief for more than a few seconds.
9. With the engine still running at full speed (3400
RPM), move lift lever to the lower position. Hold lift lever
in the lower position to allow the implement relief valve
to activate. The pressure gauge will display implement
relief pressure and should read as follows. After noting
pressure, return lift lever to neutral position.
Sand Pro & Infield Pro 3040/5040
A. For Sand Pro 3040 and Infield Pro 3040 ma-
chines, measured implement relief pressure should
be from 900 to 1100 PSI (62.1 to 75.9 bar).
B. For Sand Pro 5040 and Infield Pro 5040 ma-
chines, measured implement relief pressure should
be from 780 to 980 PSI (53.8 to 67.6 bar).
10.Shut off engine and record test results.
11. If charge pressure specification is not met, inspect,
repair or replace charge relief valve (R2). If implement
relief specification is not met, inspect, repair or replace
implement relief valve (R1). See Sauer–Danfoss
(Sundstrand) 15 Series Service Manual at the end of this
chapter for relief valve service information.
12.Remove pressure gauge. On Sand Pro 3040 and In-
field Pro 3040 machines, install and tighten hydrostat
test port plug. On Sand Pro 5040 and Infield Pro 5040
machines, reconnect hydraulic hose to hydrostat tee fit-
ting.
13.Make sure hydraulic tank is full (see Operator's
Manual).
SP/IP 3040
2
1
1. Hydrostat (from below)
1
4
3
1. Hydrostat (from below)
2. Hydrostat tee fitting
Page 4 – 23
Rev. A
2
Figure 17
2. Charge test port
SP/IP 5040
2
Figure 18
3. Hydraulic hose
4. Traction rod
Hydraulic System

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Infield pro 3040

Table of Contents