PDU8000 Modular Precision Power Distribution Cabinet
User Manual
4.1 Site Requirements
The PDC site requirements are as follows:
4.2 Installation Preparations
Before installation, unpack and check the product, make available all required technical
documents, tools, and materials, check the installation environment, and train onsite
installation personnel.
4.2.1 Obtaining Technical Documents
Table 4-1
Issue 01 (2016-02-27)
Far away from dust, smoke, harmful gas, and corrosive, flammable, or explosive objects.
Free of interference from strong electromagnetic fields.
Cabling space should be planned at the site, and cable ladders and cable trays should be
designed for the PDC installation position.
The levelness error of the concrete pad must be less than 10 mm.
The power grid must meet the PDC input rating requirements.
Class C surge protection must be provided.
The ground resistance of the ground grid must be within 10 ohms.
Temperature: –5° C to +40° C
Humidity: 5%–90% RH
Altitude: < 2000 m (derated when the altitude exceeds 2000 m). For the derating details,
contact Huawei technical support.
lists the technical documents required for PDC installation.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4
Installation Guide
4 Installation Guide
17