5.1 Site Requirements
The PDC site requirements are as follows:
5.2 Installation Preparations
Before installation, unpack and check the product, make available all required technical
documents, tools, and materials, check the installation environment, and train onsite
installation personnel.
5.2.1 Obtaining Tools and Materials
Table 5-1 Tools and materials
Category
Tightening
tools
Issue 07 (2019-04-15)
Far away from dust, smoke, harmful gas, and corrosive, flammable, or explosive objects.
Free of interference from strong electromagnetic fields.
Cabling space should be planned at the site, and cable ladders and cable trays should be
designed for the PDC installation position.
The installation position for the cabinet base must bear concentrated loads and have a
bearing capability greater than 10,000 kg/m
The levelness error of the concrete pad must be less than 10 mm.
The power grid must meet the PDC input rating requirements. For the PDC input
parameters, see the Schematic Diagram delivered with the product.
Class C surge protection must be provided.
Temperature: –5° C to +40° C
Relative humidity: 5%–95% RH.
Altitude: < 2000 m (derated when the altitude exceeds 2000 m). For the derating details,
contact Huawei technical support.
Tools and Materials
M5/M6/M8 Phillips
screwdriver
Copyright © Huawei Technologies Co., Ltd.
5
Installation Guide
2
.
Flat-head screwdriver
(2–5 mm)
5 Installation Guide
Adjustable wrench
17