Power-On Commissioning - Huawei PDU8000 User Manual

Modular precision power distribution cabinet
Hide thumbs Also See for PDU8000:
Table of Contents

Advertisement

PDU8000 Modular Precision Power Distribution Cabinet
User Manual
Context
Procedure
Step 1 Switch on the SPD circuit breaker, as shown in
SPD is running properly. If the SPD indicator is red, the SPD is faulty and must be replaced
immediately.
Issue 01 (2016-02-27)
6
The power-on commissioning personnel must be at least two qualified electricians, one
performing operations while the other monitors the operations and warns off irrelevant
persons.
Users are categorized as admin and operator. Admin users have more rights than operator
users.
Powering off the PDC disconnects the power supply to the downstream devices. Exercise
caution with this operation when the PDC is supplying power to a working system.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.

Power-On Commissioning

Figure
6 Power-On Commissioning
6-1. If the SPD indicator is green, the
41