Context
The cables from the power distribution unit to the cabinet rPDU are not
prefabricated and need to be prepared onsite.
Procedure
Step 1 Prepare cables.
1.
2.
3.
Issue 05 (2020-10-15)
A
Strip a cable.
NO TE
The figure uses the single-phase scenario as an example. The required stripping length
in the three-phase scenario is the same as that in the single-phase scenario.
Figure A-1 Stripping a cable (unit: mm)
Crimp a cord end terminal.
Figure A-2 Crimping a cord end terminal
(1) Cord end terminal
(Optional) For a three-core cable with a cross-sectional area of 6 mm
the cable with two layers of heat shrink tubing and use a heat gun to heat-
shrink the tubing.
Copyright © Huawei Technologies Co., Ltd.
Preparing Load Cables
(2) Cable

A Preparing Load Cables

(3) Crimping tool
2
, wrap
73