4.5.3 General Piping Guidelines

When measuring fluids that contain suspended solids, install permanent valves at regular
intervals to blow-down piping.
Blow-down all lines on new installations with compressed air or steam, and flush them with
process fluids (where possible) before connecting these lines to the transmitter Meter body.
Verify that the valves in the blow-down lines are closed tightly after the initial blow-down
procedure and each maintenance procedure thereafter.
Revision 13
ST 700 SmartLine Pressure Transmitters User's Manual
Page 25