Installation Preparation

Site Environment

When planning the site layout and equipment locations, consider the information in the next section to help
avoid equipment failures and reduce the possibility of environmentally caused shutdowns. If you are currently
experiencing shutdowns or unusually high error rates with your existing equipment, these considerations may
help you isolate the cause of failures and prevent future problems.

Power Supply Considerations

See
Power Supply Modules, on page 21
the security appliance.
When installing the chassis, consider the following:
• Check the power at the site before installing the chassis to ensure that it is "clean" (free of spikes and
• Install proper grounding for the site to avoid damage from lightning and power surges.
• The chassis does not have a user-selectable operating range. Refer to the label on the chassis for the
• Install an uninterruptible power source for your site, if possible.
• If you are using dual redundant (1+1) power supplies, we recommend that you use independent electrical

Rack Configuration Considerations

See
Rack-Mount the Chassis, on page 48
Consider the following when planning a rack configuration:
• Standard 19-in. (48.3 cm) 4-post EIA rack with mounting rails that conform to English universal hole
• The rack-mounting posts need to be 2 to 3.5 mm thick to work with the slide rail rack mounting.
• If you are mounting a chassis in an open rack, make sure that the rack frame does not block the intake
• If your rack includes closing front and rear doors, the doors must have 65 percent open perforated area
• Be sure enclosed racks have adequate ventilation. Make sure that the rack is not overly congested as each
• In an enclosed rack with a ventilation fan in the top, heat generated by equipment near the bottom of the
noise). Install a power conditioner, if necessary, to ensure proper voltages and power levels in the appliance
input voltage.
correct appliance input-power requirement.
circuits for each power supply.
spacing according to section 1 of ANSI/EIA-310-D-1992.
or exhaust ports.
evenly distributed from top to bottom to permit adequate airflow.
chassis generates heat. An enclosed rack should have louvered sides and a fan to provide cooling air.
rack can be drawn upward and into the intake ports of the equipment above it in the rack. Ensure that
you provide adequate ventilation for equipment at the bottom of the rack.
for more detailed information about the power supply modules in
for the procedure for rack-mounting the chassis.
Cisco Firepower 4110, 4120, 4140, and 4150 Hardware Installation Guide

Site Environment

45

Advertisement

Table of Contents
loading

This manual is also suitable for:

Firepower 4120Firepower 4140Firepower 4150

Table of Contents