4D Motor Controller
NOTE:
This test requires a 4D probe be connected to the system. This test requires a 4D probe to be
connected to the system.
Name: Presence Test
Description: This test detects the presence of the 4D Motor Controller.
Run Time: 00:01
If this test failed:
1.) Verify USB connection between the Host and the Main Power Supply.
2.) Verify 4D Motor Controller connections in Main Power Supply.
3.) Replace 4D Motor Controller.
Name: Version Test
Description: Displays the 4D Motor Controller version number.
Run Time: 00:01
If this test failed:
1.) Verify USB connection between the Host and the Main Power Supply.
2.) Verify 4D Motor Controller connections in Main Power Supply.
3.) Replace 4D Motor Controller.
Name: Static 3D Test
Description: Performs a basic static 3D scan using the RAB2-5 probe connected in probe socket 4.
Run Time: 00:11
If this test failed:
1.) Verify an RAB2-5 probe is connected to probe socket 4 (right-most probe socket).
2.) Verify the correct probe icon appears on the touch panel.
3.) Verify there is no red arrow in the icon indicating that no 4D Motor Controller was detected. Re-run
the 4D Motor Controller Presence Test in this case.
4.) Replace the 4D Motor Controller board.
Name: 4D Test
Description: Performs a basic 4D scan using the RAB2-5 probe connected in probe socket 4.
Run Time: 00:11
If this test failed:
1.) Verify an RAB2-5 probe is connected to probe socket 4 (right-most probe socket).
2.) Verify the correct probe icon appears on the touch panel.
3.) Verify there is no red arrow in the icon indicating that no 4D Motor Controller was detected. Re-run
the 4D Motor Controller Presence Test in this case.
4.) Replace the 4D Motor Controller board.
7 - 74