1. Press the Power On/Off switch to power off the system.
See 'Power Off' on page 1-25 for more information.
2. Unplug the power cord.
3. All cables from off-board peripheral devices (external Color
Digital/Report printer, etc.) and the ethernet connection
must be disconnected from the console.
4. Ensure that no loose items are left on the console.
5. Wind the power cable around the cable hook below the rear
handle.
To prevent damage to the Power Cord, DO NOT pull
excessively on the cord or make sharp bends while
wrapping.
6. Connect all probes to be used while off site. Ensure that
probe cables are out of the way from the wheels and not
protruding beyond the console. Use the probe management
hooks located below the Operator Panel to further secure
the probe cables.
If more than four (4) probes are intended to be used, store
the additional probes securely.
7. Store all other probes in their original cases or in soft cloth
or foam to prevent damage.