Installation
When replacing test point port plugs, torque from 5 to 8 ft-lbs (6.8 to 10.8 Nm).
Note
Strand Mounting the Node
The following procedure explains how to install the node on a strand (aerial installation). Strand mounting
allows street-side access to the housing, and the housing does not need to be opened.
Warning
• Be aware of the size and weight of the node while strand mounting. Ensure that the strand can safely
• Ensure the ground area below the installation site is clear of personnel before hoisting the node. If
• Failure to observe these admonishments can result in serious injury or death.
1 Check the strand size. The minimum strand diameter should be 5/16 inch.
2 Attach the strand clamp brackets to the housing in the position shown in the following illustration. Use a
torque wrench tightens the strand clamp bracket bolts from 5 ft-lb to 8 ft-lbs (6.8 to 10.8 Nm).
support the node's maximum weight. A fully loaded node weighs over 50 lbs (22.7 kg).
possible, block off walkway below the hoisting area to prevent pedestrian traffic during hoisting.
Cisco GS7000 Super High Output Intelligent Node Installation and Operation Guide
Strand Mounting the Node
17