E1 Connection Test
E1 Connection Test
The E1 tests the connection between the Site Controller and the CNE core router. All applications that
communicate with the CNE utilize the Internet Protocol (IP). The current state and statistics for IP may be
obtained using the netstat and netstat -s commands. The correct functioning of the IP layer may be determined
through careful use of the ping command. For more information refer to "MTS Interface Commands" booklet.
Enter the following loopback test command in Site Controller Test Application: e1el. MMI
modes are described in
X.21 Connection Test
Enter the following loopback test command in Site Controller Test Application: e1el. MMI
modes are described in
Site Reference Check
The SRI status is checked from the Site Controller Application. MMI modes are described
in
"MMI Commands and MTS Modes of
Verify the GPS Receiver status as follows:
At the prompt, type: status sri
Verify that:
•
•
The GPS LED will flash satellite tracking commences and will be fully on once GPS is fully trained.
6-12
The E1 connection test requires that the Site Controller is connected to an active E1 line.
"MMI Commands and MTS Modes of
The X.21 connection test requires the Site Controller to be connected to a Network
Terminating Unit (NTU) which supports the X.21 loop 3 command.
"MMI Commands and MTS Modes of
GPS State is "GPS 3D FIX" or "GPS POSITION HOLD" depending on
the type of GPSR (internal/external)
GPS Operating OK is "YES"
Operation".
Operation".
Operation".
Chapter 6: Configuration and Testing
6802800U74-N September 2009