Installing A 4G Module Or Network Cable - Huawei UPS5000-E-200K-SM User Manual

50 kva power modules
Hide thumbs Also See for UPS5000-E-200K-SM:
Table of Contents

Advertisement

UPS5000-E-(200 kVA-300 kVA)
User Manual (50 kVA Power Modules)
Figure 3-17 Installing leveling feet
Step 2 Secure the IP21 component to the top of each cabinet.
Figure 3-18 Installing the IP21 component
----End

3.2.3.3 Installing a 4G Module or Network Cable

If the iManager-M service is chosen, use either of the following methods to
complete the installation.
4G Module Access Scenario
Step 1 If the 4G module does not have a built-in SIM card, remove the 4G module
enclosure, install a SIM card, and reinstall the enclosure.
Issue 17 (2023-07-10)
NO TE
● Refer to the "front" and "back" silk screens on the surface of the IP21 component.
● Select the mounting holes for leveling feet based on the cabinet width onsite.
Copyright © Huawei Digital Power Technologies Co., Ltd.
3 Installation
85