Checking Before Power-On

Check Item
Equipment appearance
Cable appearance
Cable connections
Cable layout
Switch
Copyright © Huawei Technologies Co., Ltd.
6 Checking Before Power-On
Acceptance Criteria
● The equipment is intact and free from
rust or paint flake-off. If paint flakes off,
repaint the equipment.
● The labels on the equipment are clear.
Damaged labels must be replaced.
● Cable sheathings are properly wrapped
and not damaged.
● Cable hoses are intact.
● Cables are connected in the designed
positions.
● Terminals are prepared as required and
securely connected.
● Labels on both ends of each cable are
clear and specific, and attached in the
same direction.
● Electrical and ELV cables are routed
separately.
● Cables are neat and tidy.
● Cable tie joints are evenly cut without
burrs.
● Cables are placed properly and reserve
some slack at bending points to avoid
stress.
● Cables are routed neatly without twists
or crossovers in the cabinet.
● The DC LV Panel switch is set to OFF.
● The battery rack switch is set to OFF.