6

Power-On Commissioning

Connecting the Battery Supply
6.1

Product Overview

After turning on the battery switch, power on the inverter. For details about how to power on
the inverter, see the quick guide for the corresponding inverter model.
If no PV module is configured, press the black start button.
Turn on the DC switch on the battery. After the battery is installed and powered on for the first
time, the ring LED blinks for three circles. Touch the LED and observe the battery indicator to check
the running status.
Type
Status (Blinking at long
intervals: On for 1s and then
Off for 1s; Blinking at short
Intervals: On for 0.2s and then
Off for 0.2s)
Running
indication
Steady green
Blinking green
at long
intervals
Off
Blinking red
at short
intervals
N/A
Steady red
N/A
Battery
system
indication
Touch to display green
Steady red
Battery Deployment
6.2
Download and install the FusionSolar app of the latest version by
referring to the quick guide for the corresponding inverter model or
the FusionSolar App Quick Guide. Register as an installer and create a
PV plant or owner (skip this step if an account exists). You can obtain
the FusionSolar App Quick Guide by scanning the QR code.
Meaning
N/A
Steady green
Operating mode
Blinking green
at long
Standby mode
intervals
Off
Sleep mode
N/A
Battery power control module environment alarm
Blinking red at
Battery expansion module environment alarm
short intervals
N/A
Battery power control module fault
Steady red
Battery expansion module fault
N/A
Indicates battery level. One bar represents 10%.
The first three bars indicate the number of faulty
battery expansion modules.